Lean redesign proposal for a paint-mixing system assembly
Time study, value stream map and 5-Whys on the assembly of a two-component paint mixing & dosing system. Only 15.5 of 666 lead-time hours added value — so we proposed fixing the flow.
Loading the interactive demo…
Problem
Assembling one mixing system took 15.5 h of work but 666.65 h of lead time. Operators walked for tools, waited for parts, picked the wrong fittings and redid work when customers changed specs.
What I did
Mapped the current value stream, costed five wastes, ran 5-Whys on each, and proposed an assembly cell with 5S, a kanban + poka-yoke loop and a standard procedure, phased over 6 weeks.
Result
Estimated $16,513/year in savings for a $12,390 investment: a 9-month payback. The plan stayed a proposal.
01My role
One of five Bradley M.S. students, working with the company’s service, operations and sales managers. My part: mapping the assembly workflow and its waste, redesigning the layout and the dedicated work-cell proposal. The analysis and the deck were a team effort.
02Current state
Loading the interactive demo…
03Five wastes, costed
Loading the interactive demo…
04Root causes
Loading the interactive demo…
05Key decisions
Fix flow, not capacity
At 15 units a year takt is 133 h per unit against 15.5 h of processing. The line wasn’t short of capacity; work was waiting.
Mistake-proof the spec gate
Over-processing came from customers changing specs after parts were ordered. A kanban + checklist forces a customer check-in before purchasing.
Conservative savings
Savings assume 75% fewer defects and 80% less motion — not perfection.
Phase it
A 6-week plan: build the cell, then kanban and poka-yoke, then the SOP and training.
06Estimated results
These are the team’s estimates in the final deck (labour at $25/h plus overhead, 15 units a year). The proposal was not implemented.